§ 101.817 Notification of station operation at temporary locations.
(a) The licensee of stations authorized pursuant to § 101.813 must
notify the Commission prior to each period of operation. This
notification must include:
(1) The call sign, manufacturer's name, type or model number, output
power and specific location of the transmitter(s);
(2) The maintenance location for the transmitter;
(3) The location of the transmitting or receiving station with which it
will communicate and the identity of the correspondent operating such
facilities;
(4) The exact frequency or frequencies to be used;
(5) The public interest, convenience and necessity to be served by
operation of the proposed installation;
(6) The commencement and anticipated termination dates of operation
from each location. In the event the actual termination date differs
from the previous notification, written notice thereof promptly must be
given to the Commission;
(7) Where the notification contemplates initially a service that is to
be rendered for a period longer than 90 days, the notification must
contain a showing as to why application should not be made for regular
authorization; and
(8) A notification must include compliance with the provisions of
§ 101.813(c).
(b) A copy of the notification must be kept with the station license.
[ 61 FR 26677 , May 28, 1996, as amended at 63 FR 68984 Dec. 14, 1998]
return arrow Back to Top
Goto Section: 101.815 | 101.819
Goto Year: 2015 |
2017
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public