Goto Section: 74.12 | 74.14 | Table of Contents
FCC 74.13
Revised as of October 2, 2015
Goto Year:2014 |
2016
§ 74.13 Equipment tests.
(a) During the process of construction of any class of radio station listed
in this part, the permittee, without further authority of the Commission,
may conduct equipment tests for the purpose of such adjustments and
measurements as may be necessary to assure compliance with the terms of the
construction permit, the technical provisions of the application therefor,
the technical requirements of this chapter, and the applicable engineering
standards.
(b) Equipment tests may be continued so long as the construction permit
shall remain valid.
(c) The authorization for tests embodied in this section shall not be
construed as constituting a license to operate.
[ 38 FR 18378 , July 10, 1973]
return arrow Back to Top
Goto Section: 74.12 | 74.14
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public