Goto Section: 74.13 | 74.15 | Table of Contents
FCC 74.14
Revised as of October 1, 2008
Goto Year:2007 |
2009
Sec. 74.14 Service or program tests.
(a) Upon completion of construction of a radio station in accordance with
the terms of the construction permit, the technical provisions of the
application therefor, technical requirements of this chapter, and applicable
engineering standards, and when an application for station license has been
filed showing the station to be in satisfactory operating condition, the
permittee or any class of station listed in this part may, without further
authority of the Commission, conduct service or program tests.
(b) Program test authority for stations authorized under this part will
continue valid during Commission consideration of the application for
license and during this period further extension of the construction permit
is not required. Program test authority shall be automatically terminated
with final action on the application for station license.
(c) The authorization for tests embodied in this section shall not be
construed as approval by the Commission of the application for station
license.
[ 38 FR 18378 , July 10, 1973]
Goto Section: 74.13 | 74.15
Goto Year: 2007 |
2009
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public