  §  80.553   Supplemental eligibility requirements.

   An applicant for an operational fixed station must certify that:

   (a) The applicant is the licensee of a coast station;

   (b) Other suitable telecommunications facilities are not available to
   satisfy coast station requirements.

   [ 51 FR 31213 , Sept. 2, 1986, as amended at  63 FR 68956 , Dec. 14, 1998]

   