Sec. 25.164 Milestones.
(a) Licensees of geostationary orbit satellite systems other than DBS
and DARS satellite systems, including GSO MSS satellite systems,
licensed on or after August 27, 2003 will be required to comply with
the schedule set forth in paragraphs (a)(1) through (a)(4) of this
section in implementing their satellite systems, unless a different
schedule is established by Title 47, Chapter I, or by Commission
Order, or by Order adopted pursuant to delegated authority. These
dates are to be measured from the date the license is issued.
(1) One year: Enter into a binding non-contingent contract to
construct the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed
satellite system.
(3) Three years: Begin the construction of the satellite.
(4) Five years: Launch and operate the satellite.
(b) Licensees of non-geostationary orbit satellite systems other than
DBS and DARS satellite systems licensed on or after September 11,
2003, will be required to comply with the schedule set forth in
paragraphs (b)(1) through (b)(5) of this section in implementing their
satellite systems, unless a different schedule is established by Title
47, Chapter I, or by Commission Order, or by Order adopted pursuant to
delegated authority. These dates are to be measured from the date the
license is issued.
(1) One year: Enter into a binding non-contingent contract to
construct the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed
satellite system.
(3) Two years, six months: Begin the construction of the first
satellite in the licensed satellite system.
(4) Three years, six months: Launch and operate the first satellite in
the licensed satellite system.
(5) Six years: Bring all the satellites in the licensed satellite
system into operation.
(c) Licensees of all satellite systems, other than DBS and DARS
satellite systems, licensed on or after September 11, 2003, will be
required to submit a copy of their binding non-contingent contract
with the Commission on or before the date scheduled for entering into
such a contract.
(d) Licensees of all satellite systems, other than DBS and DARS
satellite systems, licensed on or after September 11, 2003, will be
required to submit information to the Commission sufficient to
demonstrate that the licensee has completed the critical design review
of the licensed satellite system on or before the date scheduled for
entering into such completion.
(e) Licensees of all satellite systems, other than DBS and DARS
satellite systems, licensed on or after September 11, 2003, will be
required to submit information to the Commission sufficient to
demonstrate that the licensee has commenced physical construction of
its licensed spacecraft on or before the date scheduled for such
commencement.
(f) In cases where the Commission grants a satellite authorization in
different stages, such as a license for a satellite system using
feeder links or intersatellite links, the earliest of the milestone
schedules shall be applied to the entire satellite system.
(g) Licensees of satellite systems that include both non-geostationary
orbit satellites and geostationary orbit satellites, other than DBS
and DARS satellite systems, and licensed on or after September 20,
2004 will be required to comply with the schedule set forth in
paragraph (a) of this section with respect to the geostationary orbit
satellites, and with the schedule set forth in paragraph (b) of this
section with respect to the non-geostationary orbit satellites.
[ 68 FR 51507 , Aug. 27, 2003, as amended at 69 FR 51587 , Aug. 20, 2004]
Goto Section: 24.163 | 24.165
Goto Year: 2004 |
2006
CiteFind - See documents on FCC website that
cite this rule
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.