Sec. 90.155 Time in which station must be placed in operation.
(a) All stations authorized under this part, except as provided in
paragraphs (b) and (d) of this section and in Secs. 90.629, 90.631(f),
90.665, and 90.685, must be placed in operation within
[[Page 433]]
eight (8) months from the date of grant or the authorization cancels
automatically and must be returned to the Commission.
(b) For local government entities only, a period longer than eight
months for placing a station in operation may be authorized by the
Commission on a case-by-case basis, where the applicant submits a
specific schedule for the completion of each portion of the entire
system, along with a showing that the system has been approved and
funded for implementation in accordance with that schedule. See also
Secs. 90.631 and 90.633.
(c) For purposes of this section, a base station is not considered
to be placed in operation unless at least one associated mobile station
is also placed in operation. See also Secs. 90.633(d) and 90.631(f).
(d) Multilateration LMS systems authorized in accordance with
Sec. 90.353 must be constructed and placed in operation within twelve
(12) months from the date of grant or the authorization cancels
automatically and must be returned to the Commission. MTA-licensed
multilateration LMS systems will be considered constructed and placed in
operation if such systems construct a sufficient number of base stations
that utilize multilateration technology (see paragraph (e) of this
section) to provide multilateration location service to a substantial
portion of at least one BTA in the MTA.
(e) A multilateration LMS station will be considered constructed and
placed in operation if it is built in accordance with its authorized
parameters and is regularly interacting with one or more other stations
to provide location service, using multilateration technology, to one or
more mobile units. Specifically, LMS multilateration stations will only
be considered constructed and placed in operation if they are part of a
system that can interrogate a mobile, receive the response at 3 or more
sites, compute the location from the time of arrival of the responses
and transmit the location either back to the mobile or to a subscriber's
fixed site.
[ 45 FR 81208 , Dec. 10, 1980, as amended at 47 FR 41044 , Sept. 16, 1982;
48 FR 51927 , Nov. 15, 1983; 54 FR 4030 , Jan. 27, 1989; 56 FR 65859 , Dec.
19, 1991; 60 FR 15252 , Mar. 23, 1995; 61 FR 6155 , Feb. 16, 1996]
Goto Section: 90.153 | 90.157
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public