Sec. 101.815 Stations at temporary fixed locations.
(a) Authorizations may be issued upon proper application for the use
of frequencies listed in Sec. 101.803 by stations in the Local
Television Transmission Service for rendition of temporary service to
subscribers under the following conditions:
(1) When a fixed station is to remain at a single location for less
than 6 months, the location is considered to be temporary. Services that
are initially known to be of longer than 6 months' duration may not be
provided under a temporary fixed authorization but rendered pursuant to
a regular license.
(2) When a fixed station authorized to operate at temporary
locations is installed and it subsequently becomes necessary for the
station to operate
[[Page 808]]
from such location for more than six months, application FCC Form 494
for a station authorization to specify the permanent location must be
filed at least thirty days prior to the expiration of the six month
period.
(3) The station must be used only for rendition of communication
service at a remote point where the provision of wire facilities is not
practicable.
(4) The antenna structure height employed at any location may not
exceed the criteria set forth in Sec. 17.7 of this chapter unless, in
each instance, authorization for use of a specific maximum antenna
structure height for each location has been obtained from the Commission
prior to erection of the antenna. See Sec. 101.125.
(5) Applications for such stations must comply with the provisions
of Sec. 101.713.
(b) Applications for authorizations to operate stations at temporary
locations under the provisions of this section may be made upon FCC Form
494. Blanket applications may be submitted for the required number of
transmitters.
(c) Prior coordination of mobile assignments will be in accordance
with the procedures in Sec. 101.103(d) except that the prior
coordination process for mobile (temporary fixed) assignments may be
completed orally and the period allowed for response to a coordination
notification may be less than 30 days if the parties agree.
Goto Section: 101.813 | 101.817
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public