Sec. 1.61 Procedures for handling applications requiring special
aeronautical study.
(a) Antenna Structure Registration is conducted by the Wireless
Telecommunications Bureau as follows:
(1) Each antenna structure owner that must notify the FAA of
proposed construction using FAA Form 7460-1 shall, upon proposing new or
modified construction, register that antenna structure with the Wireless
Telecommunications Bureau using FCC Form 854.
(2) If an Environmental Assessment is required under Sec. 1.1307,
the Bureau will address the environmental concerns prior to processing
the registration.
(3) If a final FAA determination of ``no hazard'' is not submitted
along with FCC Form 854, processing of the registration may be delayed
or disapproved.
(4) If the owner of the antenna structure cannot file FCC Form 854
because it is subject to a denial of federal benefits under the Anti-
Drug Abuse Act of 1988, 21 U.S.C. 862, the first licensee authorized to
locate on the structure must register the structure using FCC Form 854,
and provide a copy of the Antenna Structure Registration (FCC
[[Page 108]]
Form 854R) to the owner. The owner remains responsible for providing a
copy of FCC Form 854R to all tenant licensees on the structure and for
posting the registration number as required by Sec. 17.4(g) of this
chapter.
(5) Upon receipt of FCC Form 854, and attached final FAA
determination of ``no hazard,'' the Bureau prescribes antenna structure
painting and/or lighting specifications or other conditions in
accordance with the FAA airspace recommendation and returns a completed
Antenna Structure Registration (FCC Form 854R) to the registrant. If the
proposed structure is disapproved the registrant is so advised.
(b) Each operating Bureau or Office examines the applications for
Commission authorization for which it is responsible to ensure
compliance with FAA notification procedures as well as Commission
Antenna Structure Registration as follows:
(1) If Antenna Structure Registration is required, the operating
Bureau reviews the application for the Antenna Structure Registration
Number and proceeds as follows:
(i) If the application contains the Antenna Structure Registration
Number or if the applicant seeks a Cellular or PCS system authorization,
the operating Bureau processes the application.
(ii) If the application does not contain the Antenna Structure
Registration Number, but the structure owner has already filed FCC Form
854, the operating Bureau places the application on hold until
Registration can be confirmed, so long as the owner exhibits due
diligence in filing.
(iii) If the application does not contain the Antenna Structure
Registration Number, and the structure owner has not filed FCC Form 854,
the operating Bureau notifies the applicant that FCC Form 854 must be
filed and places the application on hold until Registration can be
confirmed, so long as the owner exhibits due diligence in filing.
(2) If Antenna Structure Registration is not required, the operating
Bureau processes the application.
(c) Where one or more antenna farm areas have been designated for a
community or communities (see Sec. 17.9 of this chapter), an application
proposing the erection of an antenna structure over 1,000 feet in height
above ground to serve such community or communities will not be accepted
for filing unless:
(1) It is proposed to locate the antenna structure in a designated
antenna farm area, or
(2) It is accompanied by a statement from the Federal Aviation
Administration that the proposed structure will not constitute a menace
to air navigation, or
(3) It is accompanied by a request for waiver setting forth reasons
sufficient, if true, to justify such a waiver.
Note: By Commission Order (FCC 65-455), 30 FR 7419 , June 5, 1965,
the Commission issued the following policy statement concerning the
height of radio and television antenna towers:
``We have concluded that this objective can best be achieved by adopting
the following policy: Applications for antenna towers higher than 2,000
feet above ground will be presumed to be inconsistent with the public
interest, and the applicant will have a burden of overcoming that strong
presumption. The applicant must accompany its application with a
detailed showing directed to meeting this burden. Only in the
exceptional case, where the Commission concludes that a clear and
compelling showing has been made that there are public interest reasons
requiring a tower higher than 2,000 feet above ground, and after the
parties have complied with applicable FAA procedures, and full
Commission coordination with FAA on the question of menace to air
navigation, will a grant be made. Applicants and parties in interest
will, of course, be afforded their statutory hearing rights.''
[ 28 FR 12415 , Nov. 22, 1963, as amended at 32 FR 8813 , June 21, 1967; 32 FR 20860 , Dec. 28, 1967; 34 FR 6481 , Apr. 15, 1969; 45 FR 55201 , Aug.
19, 1980; 58 FR 13021 , Mar. 9, 1993, 61 FR 4361 , Feb. 6, 1996]
Goto Section: 1.52 | 1.62
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public