  §  32.2441   Conduit systems.

   (a) This account shall include the original cost of conduit, whether
   underground, in tunnels or on bridges, which is reusable in place. It
   shall also include the cost of opening trenches and of any repaving
   necessary in the construction of conduit plant.

   (b) The cost of pumping water out of manholes and of cleaning manholes
   and ducts in connection with construction work and the cost of permits
   and privileges for the construction of cable and wire facilities shall
   be included in the account chargeable with such construction.

   (c) The cost of protective covering for buried cable shall be charged
   to Account 2423, Buried Cable, as appropriate, unless such protective
   covering is reusable in place. The amounts thus charged shall be
   included in the nonmetallic buried cable or metallic buried cable
   subsidiary record category, as appropriate.

   (d) The cost of pipes or other protective covering for underground drop
   and block wires shall be included in Account 2421, Aerial Cable, or
   Account 2423, Buried Cable, as appropriate. The amounts thus charged
   shall be included in the nonmetallic or metallic subsidiary record
   category, as appropriate.

   


Goto Section: 32.2431 | 32.2680

Goto Year: 2020 | 2022
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public