§ 74.788 Digital construction period.
(a) Except as indicated below, each original construction permit for
the construction of a new digital low power television or television
translator station shall specify a period of three years from the date
of issuance of the original construction permit within which
construction shall be completed and application for license filed.
Construction permits for the construction of a new digital low power
television or television translator station granted after the release
of the LPTV DTV Third Report and Order, MB Docket No. 03-185 (FCC
15-175) shall specify the later of either the digital transition
deadline or three years from the date of issuance of the original
construction permit within which construction shall be completed and
application for license filed.
(b) Any construction permit for which construction has not been
completed and for which an application for license or extension of time
has not been filed, shall be automatically forfeited upon expiration
without any further affirmative cancellation by the Commission.
(c) Authority delegated. (1) For the September 1, 2015 Class A
television digital construction deadline, authority is delegated to the
Chief, Media Bureau to grant an extension of time of up to six months
beyond September 1, 2015 upon demonstration by the Class A station that
failure to meet the construction deadline is due to circumstances that
are either unforeseeable or beyond the licensee's control where the
licensee has taken all reasonable steps to resolve the problem
expeditiously. For the low power television and TV translator station
digital transition deadline set forth in § 74.731(l) of this subpart,
authority is delegated to the Chief, Media Bureau to grant an extension
of time of up to six months beyond the digital transition deadline set
forth in § 74.731(l) upon demonstration that failure to meet the
construction deadline is due to circumstances that are either
unforeseeable or beyond the station's control where the station has
taken all reasonable steps to resolve the problem expeditiously.
(2) Such circumstances shall include, but shall not be limited to:
(i) Inability to construct and place in operation a facility necessary
for transmitting digital television, such as a tower, because of delays
in obtaining zoning or FAA approvals, or similar constraints;
(ii) The lack of equipment necessary to obtain a digital television
signal; or
(iii) Where the cost of construction exceeds the station's financial
resources.
(3) Applications for extension of time filed by Class A television
stations shall be filed not later than May 1, 2015 absent a showing of
sufficient reasons for late filing. Applications for extension of time
filed by low power television and TV translator stations shall be filed
not later than four months before the digital transition deadline set
forth in § 74.731(l) of this subpart absent a showing of sufficient
reasons for late filing.
(d) For Class A television digital construction deadlines occurring
after September 1, 2015, the tolling provisions of § 73.3598 shall
apply. For low power television and TV translator digital construction
deadlines occurring after the digital transition deadline set forth in
§ 74.731(l) of this subpart, the tolling provisions of § 73.3598 shall
apply.
(e) A low power television, TV translator or Class A television station
that holds a construction permit for an unbuilt analog and
corresponding unbuilt digital station and fails to complete
construction of the analog station by the expiration date on the analog
construction permit shall forfeit both the analog and digital
construction permits notwithstanding a later expiration date on the
digital construction permit.
(f) A low power television, TV translator or Class A television station
that holds a construction permit for an unbuilt analog and
corresponding unbuilt digital station and completes construction of the
digital station by the expiration date on the analog construction
permit, begins operating and files a license application for the
digital station may forego construction of the unbuilt analog station.
[ 69 FR 69334 , Nov. 29, 2004, as amended at 76 FR 44828 , July 27, 2011;
81 FR 5053 , Feb. 1, 2016]
return arrow Back to Top
Goto Section: 74.787 | 74.789
Goto Year: 2018 |
2020
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public