§ 17.7 Antenna structures requiring notification to the FAA.
A notification to the FAA is required, except as set forth in paragraph
(e) of this section, for any of the following construction or
alteration:
(a) Any construction or alteration of more than 60.96 meters (200 feet)
in height above ground level at its site.
(b) Any construction or alteration that exceeds an imaginary surface
extending outward and upward at any of the following slopes:
(1) 100 to 1 for a horizontal distance of 6.10 kilometers (20,000 feet)
from the nearest point of the nearest runway of each airport described
in paragraph (d) of this section with its longest runway more than 0.98
kilometers (3,200 feet) in actual length, excluding heliports.
(2) 50 to 1 for a horizontal distance of 3.05 kilometers (10,000 feet)
from the nearest point of the nearest runway of each airport described
in paragraph (d) of this section with its longest runway no more than
0.98 kilometers (3,200 feet) in actual length, excluding heliports.
(3) 25 to 1 for a horizontal distance of 1.52 kilometers (5,000 feet)
from the nearest point of the nearest landing and takeoff area of each
heliport described in paragraph (d) of this section.
(c) When requested by the FAA, any construction or alteration that
would be in an instrument approach area (defined in the FAA standards
governing instrument approach procedures) and available information
indicates it might exceed an obstruction standard of the FAA.
(d) Any construction or alteration on any of the following airports and
heliports:
(1) A public use airport listed in the Airport/Facility Directory,
Alaska Supplement, or Pacific Chart Supplement of the U.S. Government
Flight Information Publications;
(2) A military airport under construction, or an airport under
construction that will be available for public use;
(3) An airport operated by a Federal agency or the United States
Department of Defense.
(4) An airport or heliport with at least one FAA-approved instrument
approach procedure.
(e) A notification to the FAA is not required for any of the following
construction or alteration:
(1) Any object that will be shielded by existing structures of a
permanent and substantial nature or by natural terrain or topographic
features of equal or greater height, and will be located in the
congested area of a city, town, or settlement where the shielded
structure will not adversely affect safety in air navigation;
(2) Any air navigation facility, airport visual approach or landing
aid, aircraft arresting device, or meteorological device meeting
FAA-approved siting criteria or an appropriate military service siting
criteria on military airports, the location and height of which are
fixed by its functional purpose;
(3) Any antenna structure of 6.10 meters (20 feet) or less in height,
except one that would increase the height of another antenna structure.
Note to § 17.7: Consideration to aeronautical facilities not in
existence at the time of the filing of the application for radio
facilities will be given only when proposed airport construction or
improvement plans are on file with the Federal Aviation Administration
as of the filing date of the application for such radio facilities.
[ 39 FR 7581 , Feb. 27, 1974, as amended at 39 FR 26157 , July 17, 1974;
42 FR 54823 , Oct. 11, 1977; 42 FR 57127 , Nov. 1, 1977; 79 FR 56986 ,
Sept. 24, 2014]
return arrow Back to Top
Goto Section: 17.6 | 17.8
Goto Year: 2018 |
2020
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public