§ 4.15 Submarine cable outage reporting.
(a) Definitions. (1) For purposes of this section, “outage” is defined
as a failure or significant degradation in the performance of a
licensee's cable service regardless of whether the traffic can be
re-routed to an alternate path.
(2) An “outage” requires reporting under this section when there is:
(i) An outage, including those caused by planned maintenance, of a
portion of submarine cable system between submarine line terminal
equipment (SLTE) at one end of the system and SLTE at another end of
the system for more than 30 minutes; or
(ii) The loss of any fiber pair, including losses due to terminal
equipment, on a cable segment for four hours or more, regardless of the
number of fiber pairs that comprise the total capacity of the cable
segment.
(b) Outage reporting. (1) For each outage that requires reporting under
this section, the licensee (or Responsible Licensee as designated by a
Consortium) shall provide the Commission with a Notification, Interim
Report (subject to the limitations on planned outages in Section
4.15(b)(2)(iii)), and a Final Outage Report.
(i) For a submarine cable that is jointly owned and operated by
multiple licensees, the licensees of that cable may designate a
Responsible Licensee that files outage reports under this rule on
behalf of all licensees on the affected cable.
(ii) Licensees opting to designate a Responsible Licensee must jointly
notify the Chief of the Public Safety and Homeland Security Bureau's
Cybersecurity and Communications Reliability Division of this decision
in writing. Such notification shall include the name of the submarine
cable at issue; and contact information for all licensees on the
submarine cable at issue, including the Responsible Licensee.
(2) Notification, Interim, and Final Outage Reports shall be submitted
by a person authorized by the licensee to submit such reports to the
Commission.
(i) The person submitting the Final Outage Report to the Commission
shall also be authorized by the licensee to legally bind the provider
to the truth, completeness, and accuracy of the information contained
in the report. Each Final report shall be attested by the person
submitting the report that he/she has read the report prior to
submitting it and on oath deposes and states that the information
contained therein is true, correct, and accurate to the best of his/her
knowledge and belief and that the licensee on oath deposes and states
that this information is true, complete, and accurate.
(ii) The Notification is due within 480 minutes (8 hours) of the time
of determining that an event is reportable for the first three years
from the effective date of these rules. After three years from the
effective date of the rules, Notifications shall be due within 240
minutes (4 hours). The Notification shall be submitted in good faith.
Licensees shall provide: The name of the reporting entity; the name of
the cable and a list of all licensees for that cable; the date and time
of onset of the outage, if known (for planned events, this is the
estimated start time/date of the repair); a brief description of the
event, including root cause if known; nearest cable landing station;
best estimate of approximate location of the event, if known (expressed
in either nautical miles and the direction from the nearest cable
landing station or in latitude and longitude coordinates); best
estimate of the duration of the event, if known; whether the event is
planned or unplanned; and a contact name, contact email address, and
contact telephone number by which the Commission's technical staff may
contact the reporting entity.
(iii) The Interim Report is due within 24 hours of receiving the Plan
of Work. The Interim Report shall be submitted in good faith. Licensees
shall provide: The name of the reporting entity; the name of the cable;
a brief description of the event, including root cause, if known; the
date and time of onset of the outage; nearest cable landing station;
approximate location of the event (expressed in either nautical miles
and the direction from the nearest cable landing station or in latitude
and longitude); best estimate of when the cable is scheduled to be
repaired, including approximate arrival time and date of the repair
ship, if applicable; a contact name, contact email address, and contact
telephone number by which the Commission's technical staff may contact
the reporting entity. The Interim report is not required where the
licensee has reported in the Notification that the outage at issue is a
planned outage.
(iv) The Final Outage Report is due seven (7) days after the repair is
completed. The Final Outage Report shall be submitted in food faith.
Licensees shall provide: The name of the reporting entity; the name of
the cable; whether the outage was planned or unplanned; the date and
time of onset of the outage (for planned events, this is the start date
and time of the repair); a brief description of the event, including
the root cause if known; nearest cable landing station; approximate
location of the event (expressed either expressed in either nautical
miles and the direction from the nearest cable landing station or in
latitude and longitude coordinates); duration of the event, as defined
in paragraph (a)(2) of this section; the restoration method; and a
contact name, contact email address, and contact telephone number by
which the Commission's technical staff may contact the reporting
entity. If any required information is unknown at the time of
submission of the Final Report but later becomes known, licensees
should amend their report to reflect this knowledge. The Final Report
must also contain an attestation as described in paragraph (b)(2)(i) of
this section.
(v) The Notification, Interim Report, and Final Outage Reports are to
be submitted electronically to the Commission. “Submitted
electronically” refers to submission of the information using
Commission-approved Web-based outage report templates. If there are
technical impediments to using the Web-based system during the
Notification stage, then a written Notification to the Commission by
email to the Chief, Public Safety and Homeland Security Bureau is
permitted; such Notification shall contain the information required.
Electronic filing shall be effectuated in accordance with procedures
that are specified by the Commission by public notice.
(c) Confidentiality. Reports filed under this part will be presumed to
be confidential. Public access to reports filed under this part may be
sought only pursuant to the procedures set forth in 47 CFR 0.461.
Notice of any requests for inspection of outage reports will be
provided pursuant to 47 CFR 0.461(d)(3).
[ 81 FR 52363 , Aug. 8, 2016]
Effective Date Note: At 81 FR 52363 , Aug. 8, 2016, § 4.15 was added.
This section contains information collection and recordkeeping
requirements and will not become effective until approval has been
given by the Office of Management and Budget.
return arrow Back to Top
Need assistance?
Goto Section: 4.13 | 4.15
Goto Year: 2017 |
2019
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public