Goto Section: 22.721 | 22.725 | Table of Contents

FCC 22.723
Revised as of October 1, 2018
Goto Year:2017 | 2019
  § 22.723   Secondary site-by-site authorizations.

   Authorizations for new facilities (including new sites and additional
   channel pairs for existing sites) in the Rural Radiotelephone Service
   (including BETRS facilities) may be granted after May 12, 1997 only on
   the condition that such authorizations shall be secondary to any
   existing or future co-channel paging geographic area authorization in
   the Paging and Radiotelephone Service or the Rural Radiotelephone
   Service. If the paging geographic area licensee notifies the Rural
   Radiotelephone Service licensee that operation of a co-channel
   secondary facility must be discontinued because it may cause
   interference to existing or planned facilities, the Rural
   Radiotelephone Service licensee must discontinue operation of that
   facility on the particular channel pair involved no later than six
   months after such notice.

   [ 62 FR 11636 , Mar. 12, 1997]

   return arrow Back to Top


Goto Section: 22.721 | 22.725

Goto Year: 2017 | 2019
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public