§ 90.685 Authorization, construction and implementation of EA licenses.
(a) EA licenses in the 809-824/854-869 MHz band will be issued for a term
not to exceed ten years. Additionally, EA licensees generally will be
afforded a renewal expectancy only for those stations put into service after
August 10, 1996.
(b) EA licensees in the 809-824/854-869 MHz band must, within three years of
the grant of their initial license, construct and place into operation a
sufficient number of base stations to provide coverage to at least one-third
of the population of its EA-based service area. Further, each EA licensee
must provide coverage to at least two-thirds of the population of the
EA-based service area within five years of the grant of their initial
license. EA-based licensees may, in the alternative, provide substantial
service to their markets within five years of the grant of their initial
license. Substantial service shall be defined as: “Service which is sound,
favorable, and substantially above a level of mediocre service.”
(c) Channel use requirement. In addition to the population coverage
requirements described in this section, we will require EA licensees in
Channel blocks A, B and C in the 816-821/861-866 MHz band to construct 50
percent of the total channels included in their spectrum block in at least
one location in their respective EA-based service area within three years of
initial license grant and to retain such channel usage for the remainder of
the construction period.
(d) An EA licensee's failure to meet the population coverage requirements of
paragraphs (b) and (c) of this section, will result in forfeiture of the
entire EA license. Forfeiture of the EA license, however, would not result
in the loss of any constructed facilities authorized to the licensee prior
to the date of the commencement of the auction for the EA licenses.
(e) EA licensees operating on channels listed in § 90.614(b) and (c) must
implement an Enhanced Specialized Mobile Radio (ESMR) system—as defined in
§ 90.7—on their EA license and any associated site-based licenses prior to
the expiration date of the EA license. EA licensees operating on these
channels shall follow the construction notification procedures set forth in
§ 1.946(d) of this chapter. Failure to implement an ESMR system on their EA
and site-based licenses before the expiration date of the EA license will
result in termination of the EA license and any associated site-based
licenses pursuant to § 1.946(c) of this chapter.
[ 62 FR 41216 , July 31, 1997, as amended at 69 FR 67852 , Nov. 22, 2004; 70 FR 6760 , Feb. 8, 2005; 70 FR 76712 , Dec. 28, 2005]
return arrow Back to Top
Goto Section: 90.683 | 90.687
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public