§ 73.702 Assignment and use of frequencies.
(a) Frequencies will be assigned by the Commission prior to the start of
each season to authorized international broadcasting stations for use during
the season at specified hours and for transmission to specified zones or
areas of reception, with specified power and antenna bearing. Six months
prior to the start of each season, licensees and permittees shall by
informal written request, submitted to the Commission in triplicate,
indicate for the season the frequency or frequencies desired for
transmission to each zone or area of reception specified in the license or
permit, the specific hours during which it desires to transmit to such zones
or areas on each frequency, and the power, antenna gain, and antenna bearing
it desires to use. Requests will be honored to the extent that interference
and propagation conditions permit and that they are otherwise in accordance
with the provisions of this section.
(b) After necessary processing of the requests required by paragraph (a) of
this section, the Commission will notify each licensee and permittee of the
frequencies, hours of use thereof to specified zones or areas of reception,
power, and antenna bearing which it intends to authorize for the season in
question. After receipt of such notification, the licensee or permittee
shall, in writing, not later than two months before the start of the season
in question, inform the Commission either that it plans to operate in
accordance with the authorization which the Commission intends to issue, or
that it plans to operate in another manner. If the licensee or permittee
indicates that it plans to operate in another manner, it shall furnish
explanatory details.
(c) If after submitting the request required under the provisions of
paragraph (a) of this section, but before receipt of the Commission's
notification referred to in paragraph (b) of this section, the licensee or
permittee submits a request for changes of its original request, such
requests will be accepted for consideration only if accompanied by
statements showing good cause therefor and will be honored only if
conditions permit. If the information required to be submitted by the
licensee or permittee under the provisions of paragraph (b) of this section
indicates that operation in another manner is contemplated, and the
explanatory details contain a request for change in the originally proposed
manner of operation, such requests will be accepted for consideration only
if accompanied by statements showing good cause therefor and will be honored
only if conditions permit. If after the licensee or permittee submits the
information required under the provisions of paragraph (b) of this section,
but before the start of the season in question, the licensee or permittee
submits a request for changes in its manner of operation for the season in
question, the request will be accepted for consideration only if accompanied
by statements showing good cause therefor and will be honored only if
conditions permit. If after the start of a season the licensee or permittee
submits a request for changes in the manner of operation as authorized, the
request will be considered only if accompanied by statements showing good
cause therefor, and will be honored only if conditions permit.
(d) The provisions of paragraphs (a), (b), and (c) of the section shall
apply to licensees, to permittees operating under program test authority,
and to permittees who anticipate applying for and receiving program test
authority for operation during the specified season.
Note: Permittees who during the process of construction wish to engage in
equipment tests shall by informal written request, submitted to the
Commission in triplicate not less than 30 days before they desire to begin
such testing, indicate the frequencies they desire to use for testing and
the hours they desire to use those frequencies. No equipment testing shall
occur until the Commission has authorized frequencies and hours for such
testing. Such authorizations shall be only for one season, and if it is
desired to continue equipment testing in a following season, new requests
for frequencies and hours must be submitted at least 30 days before it is
desired to begin testing in the following season.
(e) Within 14 days after the end of each season, a report shall be filed
with the Commission by each licensee or permittee operating under program
test authority who has been issued a seasonal schedule for that season. The
report shall state whether the licensee or permittee has operated the number
of frequency-hours authorized by the seasonal schedule to each of the zones
or areas of reception specified in the schedule. If such operation has not
occurred, a detailed explanation of that fact shall also be submitted which
includes specific dates, frequency-hours not used, and reasons for the
failure to operate as authorized. The report shall also contain information
that has been received by the licensee or permittee as to reception or
interference, and conclusions with regard to propagation characteristics of
frequencies that were assigned for the season in question.
(f) Assigned frequencies. To the extent practicable, the frequencies
assigned to international broadcast stations shall be within the following
frequency bands, which are allocated to the broadcasting service on a
primary and exclusive basis, except as noted in paragraph (f)(1)(ii) of this
section:
(1) In all Regions:
(i) Exclusive: 5,900-6,200 kHz; 7,300-7,350 kHz; 9,400-9,900 kHz;
11,600-12,100 kHz; 13,570-13,870 kHz; 15,100-15,800 kHz; 17,480-17,900 kHz;
18,900-19,020 kHz; 21,450-21,850 kHz; and 25,670-26,100 kHz.
(ii) Co-primary: 7,350-7,400 kHz, except in the countries listed in 47 CFR
2.106, footnote 5.143C, where this band is also allocated to the fixed
service on a primary basis.
(2) In Region 1 and Region 3: 7,200-7,300 kHz and 7,400-7,450 kHz.
Note to paragraph (f): For the allocation of frequencies, the ITU has
divided the world into three Regions, which are defined in 47 CFR 2.104(b).
The bands 7,200-7,300 kHz and 7,400-7,450 kHz are not allocated to the
broadcasting service in Region 2. Subject to not causing harmful
interference to the broadcasting service, fixed and mobile services may
operate in certain of the international broadcasting bands; see 47 CFR
2.106, footnotes 5.136, 5.143, 5.143A, 5.143B, 5.143D, 5.146, 5.147, and
5.151.
(g) [Reserved]
(h) Requirements for Regional operation. (1) Frequency assignments in the
bands 7,200-7,300 kHz and 7,400-7,450 kHz shall be restricted to
international broadcast stations in the Pacific insular areas that are
located in Region 3 (as defined in 47 CFR 2.105(a), note 3) that transmit to
geographical zones and areas of reception in Region 1 or Region 3.
(2) During the hours of 0800-1600 UTC (Coordinated Universal Time) antenna
gain with reference to an isotropic radiator in any easterly direction that
would intersect any area in Region 2 shall not exceed 2.15 dBi, except in
the case where a transmitter power of less than 100 kW is used. In this
case, antenna gain on restricted azimuths shall not exceed that which is
determined in accordance with equation below. Stations desiring to operate
in this band must submit sufficient antenna performance information to
ensure compliance with these restrictions. Permitted gain for transmitter
powers less than 100 kW:
eCFR graphic er10au05.065.gif
View or download PDF
Where:
Gi = maximum gain permitted with reference to an isotropic radiator.
Pa = Transmitter power employed in kW.
(i) Frequencies requested for assignment must be as near as practicable to
the optimum working frequency (unless otherwise justified) for the zone or
area of reception for the period and path of transmission, and should be
chosen so that a given frequency will provide the largest period of reliable
transmission to the selected zone or area of reception. Moreover, at the
zone or area of reception frequencies shall provide protection to the
transmissions of other broadcasting stations which, in the opinion of the
Commission, have priority of assignment.
Note 1: Requests for frequency-hours shall be accompanied by all pertinent
technical data with reference to the frequencies and hours of operation,
including calculated field strengths delivered to the zones or areas of
reception.
Note 2: It is preferable that calculated field strengths delivered to zones
or areas of reception be equal to or greater than those required by I.F.R.B.
Technical Standards, Series A (and supplements thereto), in order for the
I.F.R.B. to afford the notified assignment protection from interference.
Nevertheless, calculated field strengths less than those required by the
I.F.R.B. standards for protection will be acceptable to the Commission.
However, licensees should note that if such lesser field strengths are
submitted no protection from interference will be provided by the I.F.R.B.
if their technical examination of such notifications show incompatibilities
with other notified assignments fully complying with I.F.R.B. technical
standards.
Note 3: Licensees are permitted to engage in multiple operation as defined
in § 73.701(d).
Note 4: Seasonal requests for frequency-hours will be only for transmissions
to zones or areas of reception specified in the basic instrument of
authorization. Changes in such zones or areas will be made only on separate
application for modification of such instruments.
(j) Not more than one frequency will be assigned for use at any one time for
any one program transmission except in instances where a program is intended
for reception in more than one zone or area of reception and the intended
zones or areas cannot be served by a single frequency: Provided, however,
That on a showing of good cause a licensee may be authorized to operate on
more than one frequency at any one time to transmit any one program to a
single zone or area of reception.
(k) Any frequency assigned to a licensee or permittee shall also be
available for assignment to other licensees or permittees.
(l) All assignments of frequencies and the hours during which they will be
used will be made with the express understanding that they are subject to
immediate cancellation or change without hearing whenever the Commission
determines that interference or propagation conditions so require and that
each frequency-hour assignment for a given seasonal schedule is unique unto
itself and not necessarily available for use during a subsequent season.
(m) The total maximum number of frequency-hours which will be authorized to
all licensees of international broadcasting stations during any one day for
any season is 100. The number of frequency-hours allocated to any licensee
will depend on past usage, availability, and need. If for a forthcoming
season the total of the requests for daily frequency-hours of all licensees
exceeds 100, all licensees will be notified and each licensee that makes an
adequate showing that good cause exists for not having its requested number
of frequency-hours reduced and that operation of its station without such
reduction would be consistent with the public interest may be authorized the
frequency-hours requested.
Note: The provisions of this paragraph are not to be construed to mean that
a total of 100 (or more) frequency-hours per day is assured licensees.
Frequency-hours will only be assigned to the extent that they are available.
It is the responsibility of each licensee to make all technical studies to
show that frequency-hours requested by it are available and suitable for use
as proposed.
[ 38 FR 18892 , July 16, 1973, as amended at 51 FR 9965 , Mar. 24, 1986; 68 FR 25538 , May 13, 2003; 70 FR 46676 , Aug. 10, 2005; 73 FR 25496 , May 6, 2008;
75 FR 63031 , Oct. 13, 2010]
return arrow Back to Top
Goto Section: 73.701 | 73.703
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public