Goto Section: 301.110 | 301.130 | Table of Contents
FCC 301.120
Revised as of October 2, 2015
Goto Year:2014 |
2016
§ 301.120 Reports on agency Transition Plans.
(a) Deadline for initial report. Not later than thirty (30) days after the
receipt of a Federal Entity's Transition Plan submitted in accordance with
applicable procedures set forth in Annex O of the NTIA Manual, the Technical
Panel shall submit to NTIA and to such Federal Entity the Technical Panel's
report on the sufficiency of the Transition Plan.
(b) Scope and content of initial report. The Technical Panel's report shall
include:
(1) A finding as to whether the Federal Entity's Transition Plan includes
the information required by the applicable provisions set forth in Annex O
of the NTIA Manual;
(2) An assessment of the reasonableness of the proposed timelines contained
in the Federal Entity's Transition Plan;
(3) An assessment of the reasonableness of the estimated relocation or
sharing costs itemized in the Federal Entity's Transition Plan, including
the costs identified by such plan for any proposed expansion of the
capabilities of the Federal Entity's system; and
(4) A conclusion, based on the finding and assessments pursuant to
paragraphs (b)(1) through (3) of this section, as to the sufficiency of the
Transition Plan.
(c) Insufficient Transition Plan. In the event the Technical Panel's initial
report concludes that the Federal Entity's Transition Plan is insufficient
pursuant to paragraph (b) of this section, the report shall also include a
description of the specific information or modifications that are necessary
for the Federal entity to include in a revised Transition Plan.
(d) Revised plan. If the Technical Panel finds the plan insufficient, the
applying Federal Entity has up to 90 days to submit to NTIA and the
Technical Panel a revised plan.
(e) Report on revised agency Transition Plans. (1) Deadline for Supplemental
Report. Not later than thirty (30) days after the receipt of a Federal
Entity's revised Transition Plan submitted after an initial or revised plan
was found by the Technical Panel to be insufficient pursuant to paragraph
(c) of this section, the Technical Panel shall submit to NTIA and to such
Federal Entity the Technical Panel's supplemental report on the sufficiency
of the revised Transition Plan.
(2) Scope and content of supplemental report. The Technical Panel's
supplemental report on the revised Transition Plan shall include:
(i) A finding as to whether the Federal Entity's revised Transition Plan
includes the necessary information or modifications identified in the
Technical Panel's initial report pursuant to paragraph (b)(1) of this
section;
(ii) A reassessment, if required, of the reasonableness of the proposed
timelines contained in the Federal Entity's revised Transition Plan;
(iii) A reassessment, if required, of the reasonableness of the estimated
relocation or sharing costs itemized in the Federal Entity's revised
Transition Plan; and
(iv) A conclusion, based on the finding and reassessments pursuant to
paragraphs (e)(2)(i) through (iii) of this section, as to the sufficiency of
the revised Transition Plan.
return arrow Back to Top
Goto Section: 301.110 | 301.130
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public