Goto Section: 301.110 | 301.130 | Table of Contents

FCC 301.120
Revised as of October 2, 2015
Goto Year:2014 | 2016
  § 301.120   Reports on agency Transition Plans.

   (a) Deadline for initial report. Not later than thirty (30) days after the
   receipt of a Federal Entity's Transition Plan submitted in accordance with
   applicable procedures set forth in Annex O of the NTIA Manual, the Technical
   Panel shall submit to NTIA and to such Federal Entity the Technical Panel's
   report on the sufficiency of the Transition Plan.

   (b) Scope and content of initial report. The Technical Panel's report shall
   include:

   (1) A finding as to whether the Federal Entity's Transition Plan includes
   the information required by the applicable provisions set forth in Annex O
   of the NTIA Manual;

   (2) An assessment of the reasonableness of the proposed timelines contained
   in the Federal Entity's Transition Plan;

   (3) An assessment of the reasonableness of the estimated relocation or
   sharing costs itemized in the Federal Entity's Transition Plan, including
   the  costs  identified  by such plan for any proposed expansion of the
   capabilities of the Federal Entity's system; and

   (4)  A  conclusion,  based  on the finding and assessments pursuant to
   paragraphs (b)(1) through (3) of this section, as to the sufficiency of the
   Transition Plan.

   (c) Insufficient Transition Plan. In the event the Technical Panel's initial
   report concludes that the Federal Entity's Transition Plan is insufficient
   pursuant to paragraph (b) of this section, the report shall also include a
   description of the specific information or modifications that are necessary
   for the Federal entity to include in a revised Transition Plan.

   (d) Revised plan. If the Technical Panel finds the plan insufficient, the
   applying  Federal  Entity  has up to 90 days to submit to NTIA and the
   Technical Panel a revised plan.

   (e) Report on revised agency Transition Plans. (1) Deadline for Supplemental
   Report. Not later than thirty (30) days after the receipt of a Federal
   Entity's revised Transition Plan submitted after an initial or revised plan
   was found by the Technical Panel to be insufficient pursuant to paragraph
   (c) of this section, the Technical Panel shall submit to NTIA and to such
   Federal Entity the Technical Panel's supplemental report on the sufficiency
   of the revised Transition Plan.

   (2)  Scope  and  content of supplemental report. The Technical Panel's
   supplemental report on the revised Transition Plan shall include:

   (i) A finding as to whether the Federal Entity's revised Transition Plan
   includes  the necessary information or modifications identified in the
   Technical  Panel's initial report pursuant to paragraph (b)(1) of this
   section;

   (ii) A reassessment, if required, of the reasonableness of the proposed
   timelines contained in the Federal Entity's revised Transition Plan;

   (iii) A reassessment, if required, of the reasonableness of the estimated
   relocation  or  sharing costs itemized in the Federal Entity's revised
   Transition Plan; and

   (iv)  A conclusion, based on the finding and reassessments pursuant to
   paragraphs (e)(2)(i) through (iii) of this section, as to the sufficiency of
   the revised Transition Plan.

   return arrow Back to Top


Goto Section: 301.110 | 301.130

Goto Year: 2014 | 2016
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public