Goto Section: 25.163 | 25.165 | Table of Contents
FCC 25.164
Revised as of October 2, 2015
Goto Year:2014 |
2016
§ 25.164 Milestones.
(a) Licensees of geostationary orbit satellite systems other than DBS and
DARS satellite systems, including GSO MSS satellite systems, licensed on or
after August 27, 2003 will be required to comply with the schedule set forth
in paragraphs (a)(1) through (a)(4) of this section in implementing their
satellite systems, unless a different schedule is established by Title 47,
Chapter I, or by Commission Order, or by Order adopted pursuant to delegated
authority. These dates are to be measured from the date the license is
issued.
(1) One year: Enter into a binding non-contingent contract to construct the
licensed satellite system.
(2) Two years: Complete the critical design review of the licensed satellite
system.
(3) Three years: Begin the construction of the satellite.
(4) Five years: Launch the space station, position it in its assigned
orbital location, and operate it in accordance with the station
authorization.
(b) Licensees of non-geostationary orbit satellite systems other than DBS
and DARS satellite systems licensed on or after September 11, 2003, will be
required to comply with the schedule set forth in paragraphs (b)(1) through
(b)(5) of this section in implementing their satellite systems, unless a
different schedule is established by Title 47, Chapter I, or by Commission
Order, or by Order adopted pursuant to delegated authority. These dates are
to be measured from the date the license is issued.
(1) One year: Enter into a binding non-contingent contract to construct the
licensed satellite system.
(2) Two years: Complete the critical design review of the licensed satellite
system.
(3) Two years, six months: Begin the construction of the first satellite in
the licensed satellite system.
(4) Three years, six months: Launch the first space station, place it in the
authorized orbit, and operate it in accordance with the station
authorization.
(5) Six years: Bring all the satellites in the licensed satellite system
into operation.
(c) Licensees of all satellite systems, other than DBS and DARS satellite
systems, must either submit a copy of a binding non-contingent satellite
construction contract with the Commission or notify the Commission in
writing that they have not entered into such a contract, no later than 15
days after the milestone date for entering into such a contract.
(d) Licensees of all satellite systems, other than DBS and DARS satellite
systems, must either submit information to the Commission sufficient to
demonstrate that the licensee has completed the critical design review of
the licensed satellite system or notify the Commission in writing that
critical design review has not been completed, no later than 15 days after
the milestone date for completion of such design review.
(e) Licensees of all satellite systems, other than DBS and DARS satellite
systems, must either submit information to the Commission sufficient to
demonstrate that the licensee has commenced physical construction of its
licensed spacecraft or notify the Commission in writing that such
construction has not commenced, no later than 15 days after the milestone
date for such commencement.
(f) Licensees of all satellite systems, other than DBS and SDARS systems,
must either demonstrate compliance with an applicable deadline for operation
or launch and operation specified in paragraph (a) or (b) of this section or
notify the Commission in writing that launch and commencement of operation
has not occurred, no later than 15 days after the deadline. Compliance with
a milestone requirement in paragraph (a)(4), (b)(4), or (b)(5) of this
section may be demonstrated by certifying pursuant to § 25.121(d) that the
space station, or stations, has, or have, been launched and placed in the
authorized orbital location or non-geostationary orbit(s) and that in-orbit
operation of the space station or stations has been tested and found to be
consistent with the terms of the authorization.
(g) Licensees of satellite systems that include both non-geostationary orbit
satellites and geostationary orbit satellites, other than DBS and DARS
satellite systems, will be required to comply with the schedule in paragraph
(a) of this section with respect to the geostationary orbit satellites, and
with the schedule set forth in paragraph (b) of this section with respect to
the non-geostationary orbit satellites.
(h) In cases where the Commission grants a satellite authorization in
different stages, such as a license for a satellite system using feeder
links or inter-satellite links, the earliest of the milestone schedules will
be applied to the entire satellite system.
[ 68 FR 51507 , Aug. 27, 2003, as amended at 69 FR 51587 , Aug. 20, 2004; 79 FR 8320 , Feb. 12, 2014]
return arrow Back to Top
Goto Section: 25.163 | 25.165
Goto Year: 2014 |
2016
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public