Goto Section: 80.551 | 80.555 | Table of Contents

FCC 80.553
Revised as of October 1, 2013
Goto Year:2012 | 2014
  §  80.553   Supplemental eligibility requirements.

   An applicant for an operational fixed station must certify that:

   (a) The applicant is the licensee of a coast station;

   (b) Other suitable telecommunications facilities are not available to
   satisfy coast station requirements.

   [ 51 FR 31213 , Sept. 2, 1986, as amended at  63 FR 68956 , Dec. 14, 1998]

   return arrow Back to Top


Goto Section: 80.551 | 80.555

Goto Year: 2012 | 2014
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public