§ 25.148 Licensing provisions for the Direct Broadcast Satellite Service.
(a) License terms. License terms for DBS facilities are specified in
§ 25.121(a).
(b) Due diligence. (1) All persons granted DBS authorizations shall
proceed with due diligence in constructing DBS systems. Permittees
shall be required to complete contracting for construction of the
satellite station(s) within one year of the grant of the authorization.
The satellite stations shall also be required to be in operation within
six years of the authorization grant.
(2) In addition to the requirements stated in paragraph (b)(1) of this
section, all persons who receive new or additional DBS authorizations
after January 19, 1996 shall complete construction of the first
satellite in their respective DBS systems within four years of grant of
the authorization. All satellite stations in such a DBS system shall be
in operation within six years of the grant of the authorization.
(3) DBS licensees shall be required to proceed consistent with all
applicable due diligence obligations, unless otherwise determined by
the Commission upon proper showing in any particular case. Transfer of
control of the authorization shall not be considered to justify
extension of these deadlines.
(c) Geographic service requirements. Those entities acquiring DBS
authorizations after January 19, 1996, or who after January 19, 1996
modify a previous DBS authorization to launch a replacement satellite,
must provide DBS service to Alaska and Hawaii where such service is
technically feasible from the authorized orbital location. This
requirement does not apply to DBS satellites authorized to operate at
the 61.5DEG W.L. orbital location. DBS applicants seeking to operate
from locations other than 61.5DEG W.L. who do not provide service to
Alaska and Hawaii, must provide technical analyses to the Commission
demonstrating that such service is not feasible as a technical matter,
or that while technically feasible such services would require so many
compromises in satellite design and operation as to make it
economically unreasonable.
(d) DBS subject to competitive bidding. Mutually exclusive initial
applications to provide DBS are subject to competitive bidding
procedures. The general competitive bidding procedures set forth in
part 1, subpart Q of this chapter will apply unless otherwise provided
in this part.
(e) DBS long form application. Winning bidders are subject to the
provisions of § 1.2107 of this chapter except that in lieu of a FCC
Form 601 each winning bidder shall submit the long-form satellite
service application (FCC Form 312) within thirty (30) days after being
notified by Public Notice that it is the winning bidder. Each winning
bidder will also be required to submit by the same deadline the
information described in § 25.215 (Technical) and § 25.601 (EEO), and
in paragraph (f) of this section. Each winner also will be required to
file, by the same deadline, a signed statement describing its efforts
to date and future plans to come into compliance with any applicable
spectrum limitations, if it is not already in compliance. Such
information shall be submitted pursuant to the procedures set forth in
§ 25.114 and any associated Public Notices.
(f) Technical qualifications. DBS operations must be in accordance with
the sharing criteria and technical characteristics contained in
Appendices 30 and 30A of the ITU's Radio Regulations. Operation of
systems using differing technical characteristics may be permitted,
with adequate technical showing, and if a request has been made to the
ITU to modify the appropriate Plans to include the system's technical
parameters.
[ 67 FR 51113 , Aug. 7, 2002]
return arrow Back to Top
Goto Section: 25.147 | 25.149
Goto Year: 2012 |
2014
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public