Goto Section: 78.22 | 78.27 | Table of Contents
FCC 78.23
Revised as of October 1, 2010
Goto Year:2009 |
2011
§ 78.23 Equipment tests.
(a) Following the grant of a CARS license, the licensee, during the
process of construction of the station, may, without further authority
from the Commission, conduct equipment tests for the purpose of such
adjustments and measurements as may be necessary to assure compliance
with the terms of the authorization, the technical provisions of the
application therefore, the rules and regulations, and the applicable
engineering standards.
(b) The Commission may notify the licensee to conduct no tests or may
cancel, suspend, or change the date for the beginning of equipment
tests as and when such action may appear to be in the public interest,
convenience, and necessity.
(c) The test authorized in this section shall be conducted only as a
necessary part of construction.
[ 50 FR 23421 , June 4, 1985]
Goto Section: 78.22 | 78.27
Goto Year: 2009 |
2011
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public