Goto Section: 90.663 | 90.667 | Table of Contents
FCC 90.665
Revised as of October 1, 2008
Goto Year:2007 |
2009
Sec. 90.665 Authorization, construction and implementation of MTA licenses.
(a) MTA licenses in the 896–901/935–940 MHz band will be issued for a term
not to exceed ten years.
(b) MTA licensees in the 896–901/935–940 MHz band will be permitted five
years to construct their stations. This five-year period will commence with
the issuance of the MTA-wide authorization and will apply to all of the
licensee's stations within the MTA spectrum block, including any stations
that may have been subject to an earlier construction deadline arising from
a pre-existing authorization.
(c) Each MTA licensee in the 896–901/935–940 MHz band must, three years from
the date of license grant, construct and place into operation a sufficient
number of base stations to provide coverage to at least one-third of the
population of the MTA; further, each MTA licensee must provide coverage to
at least two-thirds of the population of the MTA five years from the date of
license grant. Alternatively, an MTA licensee must demonstrate, through a
showing to the Commission five years from the date of license grant, that it
is providing substantial service. An MTA licensee must, three years from
license grant, either show that the1/3population coverage standard has been
satisfied, or provide written notification that it has elected to show
substantial service to the MTA five years from license grant. In addition,
as part of the election to provide a substantial service showing, each MTA
licensee must, three years from license grant, indicate how it expects to
demonstrate substantial service at five years. The MTA licensee must meet
the population coverage benchmarks regardless of the extent to which
incumbent licensees are present within the MTA block.
(d) MTA licensees who fail to meet the coverage requirements imposed at
either the third or fifth years of their license term, or to make a
convincing showing of substantial service, will forfeit the portion of the
MTA license that exceeds licensed facilities constructed and operating on
the date of the MTA license grant.
[ 60 FR 21991 , May 4, 1995, as amended at 60 FR 48918 , Sept. 21, 1995; 60 FR 61487 , Nov. 30, 1995; 64 FR 39942 , July 23, 1999]
Goto Section: 90.663 | 90.667
Goto Year: 2007 |
2009
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public