Goto Section: 27.302 | 27.308 | Table of Contents

FCC 27.303
Revised as of October 1, 2008
Goto Year:2007 | 2009
  Sec.  27.303   Upper 700 MHz commercial and public safety coordination zone.

   (a) General. CMRS operators are required, prior to commencing operations on
   fixed or base station transmitters on the 776–787 MHz and 788–793 MHz bands
   that are located within 500 meters of existing or planned public safety base
   station receivers, to submit a description of their proposed facility to a
   Commission-approved public safety coordinator.

   (1) The description must include, at a minimum;

   (i) The frequency or frequencies on which the facility will operate;

   (ii) Antenna location and height;

   (iii) Type of emission;

   (iv) Effective radiated power;

   (v) A description of the area served and the operator's name.

   (2) It is the CMRS operator's responsibility to determine whether referral
   is required for stations constructed in its area of license. Public safety
   base stations are considered “planned” when public safety operators have
   notified, or initiated coordination with, a Commission-approved public
   safety coordinator.

   (b) CMRS operators must wait at least 10 business days after submission of
   the required description before commencing operations on the referenced
   facility, or implementing modifications to an existing facility.

   (c) The potential for harmful interference between the CMRS and public
   safety facilities will be evaluated by the public safety coordinator.

   (1) With regard to existing public safety facilities, the coordinator's
   determination to disapprove a proposed CMRS facility (or modification) to be
   located within 500 meters of the public safety facilities will be presumed
   correct,  but  the  CMRS  operator  may seek Commission review of such
   determinations.  Pending Commission review, the CMRS operator will not
   activate the facility or implement proposed modifications.

   (2) With regard to proposed public safety facilities, the coordinator's
   determination to disapprove a proposed CMRS facility (or modification) to be
   located within 500 meters of the public safety facilities will be presumed
   correct, but the CMRS operator may seek Commission review and, pending
   completion of review, operate the facility during construction of the public
   safety  facilities.  If coordination or Commission review has not been
   completed when the public safety facilities are ready to operate, the CMRS
   operator  must  cease operations pending completion of coordination or
   Commission review. Such interim operation of the CMRS facility within the
   coordination zone (or implementation of modifications) will not be relied on
   by the Commission in its subsequent review and determination of measures
   necessary to control interference, including relocation or modification of
   the CMRS facility.

   (d) If, in the event of harmful interference between facilities located
   within 500 meters proximity, the parties are unable, with the involvement of
   the  coordinator,  to  resolve  the  problem  by mutually satisfactory
   arrangements, the Commission may impose restrictions on the operations of
   any of the parties involved.

   [ 67 FR 49245 , July 30, 2002, as amended at  72 FR 48853 , Aug. 24, 2007]


Goto Section: 27.302 | 27.308

Goto Year: 2007 | 2009
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public