Goto Section: 101.73 | 101.77 | Table of Contents
FCC 101.75
Revised as of October 1, 2008
Goto Year:2007 |
2009
Sec. 101.75 Involuntary relocation procedures.
(a) If no agreement is reached during the mandatory negotiation period, an
ET licensee may initiate involuntary relocation procedures under the
Commission's rules. ET licensees are obligated to pay to relocated only the
specific microwave links to which their systems pose an interference
problem. Under involuntary relocation, the FMS licensee is required to
relocate, provided that the ET licensee:
(1) Guarantees payment of relocation costs, including all engineering,
equipment, site and FCC fees, as well as any legitimate and prudent
transaction expenses incurred by the FMS licensee that are directly
attributable to an involuntary relocation, subject to a cap of two percent
of the hard costs involved. Hard costs are defined as the actual costs
associated with providing a replacement system, such as equipment and
engineering expenses. ET licensees are not required to pay FMS licensees for
internal resources devoted to the relocation process. ET licensees are not
required to pay for transaction costs incurred by FMS licensees during the
voluntary or mandatory periods once the involuntary period is initiated, or
for fees that cannot be legitimately tied to the provision of comparable
facilities;
(2) Completes all activities necessary for implementing the replacement
facilities, including engineering and cost analysis of the relocation
procedure and, if radio facilities are used, identifying and obtaining, on
the incumbents' behalf, new microwave frequencies and frequency
coordination; and
(3) Builds the replacement system and tests it for comparability with the
existing 2 GHz system.
(b) Comparable facilities. The replacement system provided to an incumbent
during an involuntary relocation must be at least equivalent to the existing
FMS system with respect to the following three factors:
(1) Throughput. Communications throughput is the amount of information
transferred within a system in a given amount of time. If analog facilities
are being replaced with analog, the ET licensee is required to provide the
FMS licensee with an equivalent number of 4 kHz voice channels. If digital
facilities are being replaced with digital, the ET licensee must provide the
FMS licensee with equivalent data loading bits per second (bps). ET
licensees must provide FMS licensees with enough throughput to satisfy the
FMS licensee's system use at the time of relocation, not match the total
capacity of the FMS system.
(2) Reliability. System reliability is the degree to which information is
transferred accurately within a system. ET licensees must provide FMS
licensees with reliability equal to the overall reliability of their system.
For digital data systems, reliability is measured by the percent of time the
bit error rate (BER) exceeds a desired value, and for analog or digital
voice transmissions, it is measured by the percent of time that audio signal
quality meets an established threshold. If an analog voice system is
replaced with a digital voice system, only the resulting frequency response,
harmonic distortion, signal-to-noise ratio and its reliability will be
considered in determining comparable reliability.
(3) Operating costs. Operating costs are the cost to operate and maintain
the FMS system. ET licensees must compensate FMS licensees for any increased
recurring costs associated with the replacement facilities ( e.g.,
additional rental payments, increased utility fees) for five years after
relocation. ET licensees may satisfy this obligation by making a lump-sum
payment based on present value using current interest rates. Additionally,
the maintenance costs to the FMS licensee must be equivalent to the 2 GHz
system in order for the replacement system to be considered comparable.
(c) The FMS licensee is not required to relocate until the alternative
facilities are available to it for a reasonable time to make adjustments,
determine comparability, and ensure a seamless handoff.
(d) Twelve-month trial period. If, within one year after the relocation to
new facilities, the FMS licensee demonstrates that the new facilities are
not comparable to the former facilities, the ET licensee must remedy the
defects or pay to relocate the microwave licensee to one of the following:
its former or equivalent 2 GHz channels, another comparable frequency band,
a land-line system, or any other facility that satisfies the requirements
specified in paragraph (b) of this section. This trial period commences on
the date that the FMS licensee begins full operation of the replacement
link. If the FMS licensee has retained its 2 GHz authorization during the
trial period, it must return the license to the Commission at the end of the
twelve months. FMS licensees relocated from the 2110–2150 and 2160–2200 MHz
bands may not be returned to their former 2 GHz channels. All other remedies
specified in paragraph (d) are available to FMS licensees relocated from the
2110–2150 MHz and 2160–2200 MHz bands, and may be invoked whenever the FMS
licensee demonstrates that its replacement facility is not comparable,
subject to no time limit.
[ 61 FR 29694 , June 12, 1996, as amended at 65 FR 48183 , Aug. 7, 2000; 68 FR 3464 , Jan. 24, 2003; 71 FR 29842 , May 24, 2006]
Goto Section: 101.73 | 101.77
Goto Year: 2007 |
2009
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public