FCC 74.34 Revised as of October 1, 2007
Goto Year:2006 |
2008
Sec. 74.34 Period of construction; certification of completion of construction.
(a) Each aural and television broadcast auxiliary station authorized under
subparts E and F of this part must be in operation within 18 months from the
initial date of grant.
(b) Each remote pickup broadcast auxiliary station authorized under subpart
D of this part must be in operation within 12 months from the initial date
of grant.
(c) Failure to timely begin operation means the authorization terminates
automatically.
(d) Requests for extension of time may be granted upon a showing of good
cause pursuant to Sec. 1.946(e) of this chapter.
(e) Construction of any authorized facility or frequency must be completed
by the date specified in the license and the Commission must be notified
pursuant to Sec. 1.946 of this chapter.
[ 68 FR 12763 , Mar. 17, 2003]
Subpart A—Experimental Broadcast Stations
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.