Goto Section: 73.7001 | 73.7003 | Table of Contents
FCC 73.7002
Revised as of October 1, 2007
Goto Year:2006 |
2008
Sec. 73.7002 Fair distribution of service on reserved band FM channels.
(a) If timely filed applications for full service stations on reserved FM
channels are determined to be mutually exclusive, and will serve different
communities, the Commission will first determine, as a threshold issue,
whether grant of a particular application would substantially further the
fair distribution of service goals enunciated in section 307(b) of the
Communications Act, 47 U.S.C. 307(b).
(b) In an analysis performed pursuant to paragraph (a) of this section, a
full service FM applicant that will provide the first or second reserved
channel noncommercial educational (NCE) aural signal received by at least
10% of the population within the station's 60dBu (1mV/m) service contours
will be considered to substantially further fair distribution of service
goals and to be superior to mutually exclusive applicants not proposing that
level of service, provided that such service to fewer than 2,000 people will
be considered insignificant. First service to 2,000 or more people will be
considered superior to second service to a population of any size. If only
one applicant will provide such first or second service, that applicant will
be selected as a threshold matter. If more than one applicant will provide
an equivalent level (first or second) of NCE aural service, the size of the
population to receive such service from the mutually exclusive applicants
will be compared. The applicant providing the most people with the highest
level of service will be awarded a construction permit, if it will provide
such service to 5,000 or more people than the next best applicant. If none
of the applicants in a mutually exclusive group would substantially further
fair distribution goals, all applicants will proceed to examination under a
point system. If two or more applicants will provide the same level of
service to an equivalent number of people (differing by less than 5,000),
only those equivalent applicants will be considered together in a point
system.
(c) For a period of four years of on-air operations, an applicant receiving
a decisive preference pursuant to this section is required to construct and
operate technical facilities substantially as proposed and shall not
downgrade service to the area on which the preference was based.
[ 65 FR 36380 , June 8, 2000, as amended at 66 FR 15356 , Mar. 19, 2001]
Goto Section: 73.7001 | 73.7003
Goto Year: 2006 |
2008
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.