Sec. 25.140 Qualifications of fixed-satellite space station licensees.
(a) New fixed-satellites shall comply with the requirements established in
Report and Order, CC Docket No. 81–704 (available at address in Sec. 0.445 of
this chapter.) Applications must also meet the requirements in paragraphs
(b) through (d) of this section. The Commission may require additional or
different information in the case of any individual application.
Applications will be unacceptable for filing and will be returned to the
applicant if they do not meet the requirements referred to in this
paragraph.
(b) Each applicant for a space station authorization in the fixed-satellite
service must demonstrate, on the basis of the documentation contained in its
application, that it is legally, technically, and otherwise qualified to
proceed expeditiously with the construction, launch and/or operation of each
proposed space station facility immediately upon grant of the requested
authorization. Each applicant must provide the following information:
(1) The information specified in Sec. 25.114; and
(2) Except as set forth in paragraph (b)(3) of this section, all applicants
must provide an interference analysis to demonstrate the compatibility of
their proposed system 2 from any authorized space station. An applicant
should provide details of its proposed r.f. carriers which it believes
should be taken into account in this analysis. At a minimum, the applicant
must include, for each type of r.f. carrier, the link noise budget,
modulation parameters, and overall link performance analysis. (See, e.g. ,
appendices B and C to Licensing of Space Stations in the Domestic
Fixed-Satellite Service (available at address in Sec. 0.445)).
(3) Applicants for licenses for satellites in the 17/24 GHz BSS must provide
an interference analysis of the kind described in paragraph (b)(2) of this
section, except that the applicant must demonstrate the compatibility of its
proposed system 4 ° from any current or future authorized space station in
the 17/24 GHz BSS that complies with the technical rules in this part. The
link budget must take into account longitudinal stationkeeping tolerances
and any existing orbital location offsets from the nominal 17/24 GHz BSS
orbital locations of the adjacent prior-authorized 17/24 GHz BSS space
stations. In addition, any 17/24 GHz BSS satellite applicant that has
reached a coordination agreement with an operator of another 17/24 GHz BSS
satellite located up to ±10 °away to allow that operator to exceed the pfd
levels specified in the rules for this service, must use those higher pfd
levels for the purposes of this showing.
(c) Any space station applicant for a space station authorization in the
17/24 GHz BSS must design its satellite network to be capable of operating
with another 17/24 GHz BSS satellite as close as four degrees away from its
17/24 GHz BSS satellite.
(d)–(g) [Reserved]
[ 62 FR 5929 , Feb. 10, 1997, as amended at 68 FR 51504 , Aug. 27, 2003; 72 FR 50028 , Aug. 29, 2007]
Goto Section: 25.139 | 25.142
Goto Year: 2006 |
2008
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public