Goto Section: 24.249 | 24.253 | Table of Contents
FCC 24.251
Revised as of October 1, 2007
Goto Year:2006 |
2008
Sec. 24.251 Dispute resolution under the Cost-Sharing Plan.
Disputes arising out of the cost-sharing plan, such as disputes over the
amount of reimbursement required, must be brought, in the first instance, to
the clearinghouse for resolution. To the extent that disputes cannot be
resolved by the clearinghouse, parties are encouraged to use expedited ADR
procedures, such as binding arbitration, mediation, or other ADR techniques.
[ 61 FR 29693 , June 12, 1996]
Goto Section: 24.249 | 24.253
Goto Year: 2006 |
2008
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public